2.3.2

Vertical Pole Installation

2.3.2.1 Round

Pole

Note: The following process is for a typical installation. Custom systems may be
ordered, and are beyond the scope of this manual.

To install the RFT to a round vertical pole:

1. Set the unit on its side, with the mounting holes facing up.

2. Install the 8” unistruts as follows:

a.

Position an 8” unistrut (with
the open side facing up)
over one set of the mounting
holes on the RFT.

b. Using four 1/4-20 bolts,

1/4” split lockwashers, and
1/4” flat washers, attach an
8” unistrut to the RFT.

Tighten the bolts firmly.

c.

Repeat Steps 2.a. and 2.b.
for the second 8” unistrut.