Holidays
Holiday Day Selection
Holiday Start/Stop Times
The screens will step through the eleven possible holidays one
at a time. Line 2 shows which holiday is currently being
programmed.
Remember to combine the month and day into a single four-
digit value.
EXAMPLE: 704 = July 4th
1225 = December 25th
Program Holidays
Holiday # 1
Start Mon/Day: 101
(EX: 101 = Jan. 1)
The eleven holidays all use the same Start and Stop
time which is entered on this screen. It is entered in 24-
hour military format, the same as a regular week
schedule.
Holiday Schedule
Starting Time: 0
Stopping Time: 0