6.3. Starting DUT Tests with NuPAD
NuPAD has 3 buttons on its front panel: “|| Pause”, “■ Stop”, and “
►
Run”. After connecting NuPAD
with NuStreams-P6GW with Cat-5 cable, you can start/pause/stop DUT tests with these 3 buttons.
Please see the table down below for a detailed description about these buttons’ functions.
Function
Button
Description
Start Testing All
Tasks in Current Run
► Run
Press “
► Run” to start all Tasks
in the current Run. The current
Run (Run 1~3) about to be
tested will be displayed on the
upper-right part of LCD.
Switching Current
Run
|| Pause
+
■Stop
To change the current Run (Run 1~3), press both “|| Pause” and
“
■Stop” buttons at the same time. If NuPAD is current in Run 1,
pressing both “|| Pause” and “
■Stop” buttons at the same time will
switch the current Run from Run 1 to Run 2.
Pause Current
Running Test
|| Pause
Press “|| Pause” button once to pause the current running test.
Press “|| Pause” button again to resume the test.
Stop Current
Running Test
■Stop
Press “
■Stop” button once to stop the current running test.