3.2. Installation for Switch Test
While performing tests on Switch, DUT LAN ports must be connected to NuStreams-P6GW with CAT-5
UTP cables or/and the DUT must detects the NuStreams-P6GW’s signal from its Wireless Module as
shown in the figure down below:
If both NuStreams-P6GW’s Switch Port 1~5 and DUT’s ports are connected via CAT-5 UTP cables
correctly, the Link/ACT LEDs 1~5 located on NuStreams-P6GW’s LAN Port Status LED will be ON
accordingly. If both Nustreams-P6GW and DUT are connected via Wireless connection, the last
Link/ACT LED (WLAN) will be ON accordingly.