beautypg.com

4 function test during commissioning, Function test during commissioning, Wiring – Pilz PSSu E F 4DO 0.5 User Manual

Page 29

background image

Wiring

Operating Manual PSSu E F 4DO 0.5(­T)(­R)
21316­EN­05

29

Dual­channel operation

Redundant actuator

With feedback loop

21

11

22

12

23

13

24

14

0 V

O0

O2

O1

O3

0 V

0 V

0 V

T0

T0

T1

I0

I1

I3

21

11

22

12

23

13

24

14

PSSu E F 4DI

K1

K2

T1

I2

K3

K4

RFK

RFK

K1

K2

K3

K4

PSSu E F 4DO 0.5

21

11

22

12

24

14

0 V

O0

O2

O1

O3

0 V

23

13

K1

K2

T0

T0

T1

I0

I1

I3

21

11

22

12

23

13

24

14

PSSu E F 4DI

K1

K2

T1

I2

RFK

PSSu E F 4DO 0.5

6.4

Function test during commissioning

An error must be simulated for each safety­related output during commissioning: The anti­
cipated error reaction must occur when an output has a short circuit to a supply voltage.

INFORMATION

The short circuit test must be performed on the load and not on the output
terminal.