Loading Material
If feeders are NOT linked...
Load material into all the feeders as indicated by the Mail Piece Icon
Tree (refer to setting the feeders on pages 3-14 to 3-19).
If feeders ARE linked...
For Job Definitions which contain linked feeders, the loading of
the feeders must be in the correct order to minimize the risk of the
sheets becoming out of sequence.
Insert Feeders
The uppermost Insert Feeder (G) should be loaded first. The
Inserts should be loaded as instructed by the loading instructions
on the control panel. If OMR marks are used on the inserts, the
marks must be
face up and nearest to the front of the machine.
For C and Double folds
Place the complete stack of Sheets to be loaded into the Linked
Feeders
face up next to the machine. Select the required
amount of sheets to be loaded into the first Sheet Feeder. Load
the sheets as indicated by the loading instructions on the control
panel into the
uppermost linked Sheet Feeder. Take the next
required amount of sheets from the top of the stack and load
these into the feeder immediately below the previous feeder.
Repeat, if necessary, until all linked feeders are loaded.
For Sngle and Z folds
Place the complete stack of Sheets to be loaded into the Linked
Feeders
face down next to the machine. Select the required
amount sheets to be loaded into the first Sheet Feeder. Load
the sheets as indicated by the loading instructions on the control
panel into the
uppermost linked Sheet Feeder. Take the next
required amount for the top of the stack and load these into
the feeder immediately below the previous feeder. Repeat, if
necessary, until all linked feeders are loaded.