beautypg.com

Installation / performance check list gas system, Refrigeration system, Electrical system – Reznor R6GN Unit Installation Manual User Manual

Page 36: Venting system

background image

INStallatIoN / PERFoRMaNcE cHEcK lISt

GaS SYStEM

Gas Type: (circle one)

Natural Gas

Propane

Gas pipe connections leak-tested?

YES

NO

Gas Line Pressure: ____________________________ (in - W.C.)

Is there adequate fresh air supply

for combustion & ventilation?

YES

NO

Installation Altitude: _________________________________ (FT.)

Deration Percentage: _________________________________ (%)

Furnace Input: ____________________________________(Btuh)

Supply Air Temperature: _____________________________ (° F)

Return Air Temperature: _____________________________ (° F)

Temperature Rise: _________________________________ (° F)

During Furnace Operation:

Low fire manifold pressure: ______________________ (in - W.C.)

High fire manifold pressure: ______________________ (in - W.C.)

REFRIGERatIoN SYStEM

Was unit given 24 hr warm up period

for crankcase heaters?

YES

NO

Did reversing valve energize?

YES

NO

Stage-1 Liquid Pressure (high side) ________________________

Stage-1 Suction Pressure (low side) ________________________

Stage-2 Liquid Pressure (high side) ________________________

Stage-2 Suction Pressure (low side) ________________________

INStallatIoN aDDRESS:

CITY ________________________ STATE ________________

UNIT MODEL # ________________________________________

UNIT SERIAL # _______________________________________

Unit Installed Minimum clearances per

Figure 1 (page 5)?

YES

NO

INStallER NaME:

CITY _______________________

STATE ________________

Has the owner’s information been

reviewed with the customer?

YES

NO

Has the Literature Package been left

with the unit?

YES

NO

ElEctRIcal SYStEM

Electrical connections tight?

YES

NO

Line voltage polarity correct?

YES

NO

Rated Voltage: ___________________________________ VOLTS

L1-L2 Volts: _____________________________________ VOLTS

L1-L3 Volts: _____________________________________ VOLTS

L2-L3 Volts: _____________________________________ VOLTS

Avg.Volts: _______________________________________ VOLTS

Max. Deviation of Voltage
From Avg Volts ___________________________________ VOLTS

% Volt Imbalance: ________________________________ VOLTS

Blower Motor HP: ________ Sheave Setting ___________# Turns

Has the thermostat been calibrated?

YES

NO

Is the thermostat level?

YES

NO

Is the heat anticipator setting correct?

YES

NO

Specifications & illustrations subject to change without notice or incurring obligations.
O’ Fallon, MO | Printed in U.S.A. (02/11)

708956B (Replaces 708956A)

VENtING SYStEM

Is the vent hood installed?

YES

NO

Is vent hood free from restrictions

YES

NO

Filter(s) secured in place?

YES

NO

Filter(s) clean?

YES

NO

*

AHRI commercial furnace certification listing applies only to 3 phase units having an input rate 225,000 Btu/hr or greater

*