Zone-plug-bridge-install-typeb – Oldcastle BuildingEnvelope ICR-225 User Manual
Page 25

22
March 2012
Phone: 1-866-OLDCASTLE (653-2278)
Web Address: www.oldcastlebe.com
I C R - 2 2 5 - I N S T A L L A T I O N M A N U A L
Figure 24
Zone Plug Installation
Bridge Installation
Figure 25
Seal Zone plug to
form a water tight
seal
ICR-107-01 Mullion (deep pocket)
ICR-110-01 Mullion (shallow pocket)
ICR-108-01 Jambs
ICR-105-01 Bridge
Attach bridges with
(2) FS-202 (#8 X 1/2" PPH)
Cap Seal Fasteners
Bed in sealant
Apply sealant to
top of Horizontal
After Bridge is installed seal joints
between Bridge and Horizontals (Typical)
Install and seal zone plugs at captured verticals as shown in
FIGURE 24 Where there are SSG
verticals, install and seal aluminum bridges per instructions in
STEP 6.5.
ZONE PLUG & BRIDGE IINSTALLATION
6.3
6.4
6.5 SSG Bridge Installation: An aluminum bridge must be installed at each horizontal to vertical connection
when using a SSG mullion. The bridge will be attached to the horizontals using (2) FS-202 #8 x ½” Pan
Head screws. Sealant will be applied to the horizontal member and to the mating surface of the bridge.
Set bridge in place and attach. Tool sealant around the perimeter of the bridge and along the face of the
mullion. Cap seal fasteners. The joint at the face of the bridge to the horizontal must also be sealed. SEE
FIGURE 25,.
Seal perimeter of frame. Care must be taken to marry seals at the corners of the frame. Interior seals
are not required for system performance, but may be necessary for cosmetic purposes. When installing
exterior seal it is recommended that the seal be applied prior to installing face caps. Keep weep holes at
sill clear of sealant. Never apply perimeter seal along outer edge of face cap.