4.3
Fabricate head & sill members for vertical/jamb attachment. Use DJ-101 drill jig to drill the holes at the
sill member and DJ-104 for the head member.
SEE FIGURE 16, page 16.
Drill jig guide:
Align drill jig with side of mullion at head & sill member. Drill holes outlined below based on the
member:
Head Member (DJ-104) – Use holes 1,2,3,4 for 4 1/2” system; A,B,C,D for 6” system
Sill Member (DJ-101) – Use holes A,B,G,H for 4 1/2” system; A,C,G,I for 6” system
NOTE: Only two (2) holes are needed for the 4 1/2” system.
Drilling four (4) holes is recommended in case verticals must be flipped for
pocket orientation.
•
•
4.4
Align drill jig DJ-103 with top of Horizontal. Fabricate vertical mullions for intermediate horizontals.
Notch top of all verticals and jambs for head member.
SEE FIGURE 16, page 16.
4.5
If horizontals are required, fabricate hole on each end of horizontal per
FIGURE 20, page 20.
4.6
Drill 5/16” diameter weep holes in horizontals and sill members at 1/4 points. Install ICR-312 baffle
clip at Horizontals and Head. Install HP-1004 baffles as required at sill, securing with SPW-295 baffle
retainers.
SEE FIGURE 18, page 18.
4.7
Drill one 5/16” diameter weep holes at the bottom center of each lite of glass at the head, sill, and
horizontal face caps. NOTE: For SSG applications, there will be multiple holes per cap.
4.8
Drill anchor holes in sill anchors (TCR-102 for 4 ½” system or ICR-103 for 6” system). Head anchors
are secured to building condition before frame is set in place. See approved shop drawings for
location and quantity of anchors and anchor bolt sizes for both head and sill anchors.
Maximum end reactions:
4 1/2” system: 600 lbs.
6” system: 1000 lbs. (Type “B”) with optional head & sill reinforcing sleeves).
•
•
FRAME FABRICATION TYPE “B”