to the general contractor and differences resolved before proceeding

and properly treated to receive sealant.

should be clean and dry. All perimeter substrate shall be cleaned

is required, including other sealant surfaces. All frame surfaces

All sealant must be compatible with all surfaces on which adhesion

dissimilar materials. Use Dow Corning 795 or equal. All sealant must

provides a resilient, flexible air and water seal between similar and

SEALANT- A weather resistant, gunnable, liquid filler which when dry

purpose of these instructions, sealant is defined as follows:

I. Throughout these instructions the term SEALANT will appear. For the

DAMAGES WHICH MAY HAVE OCCURRED.

quantities and correct finishes.

H. Verify the contents of all material shipments upon arrival. Verify

G. Follow EFCO’s framing installation and glazing instructions.

dissimilar materials, with a heavy coating of bituminous primer such

F. Coat all aluminum, to be placed directly in contact with masonry or

meet FEDERAL SPECIFICATION TT-S-00227E, TT-S-001543A, AND

further with the installation in the questionable area.

as zinc chromate.

uments. If deviations occur, notification must be given IN WRITING

receiving the installation are in accordance with the contract doc-

E. Verify that all job site conditions and accompanying substrates

with the general contractor and supervise the locations.

superintendent so delays are prevented and the risk of material

D. The sequence of erection should be coordinated with the project

damage is minimized. If preset anchors are required, coordinate

NOTE:

TT-S-00230G.

TOOLS NEEDED:

1. Wedge hammer and/or gasket roller
2. Putty knife
3. Level and square

4. Cutting tool, hand pruner, etc.

PAGE #2

SECTION I - GENERAL NOTES AND GUIDELINES

5. #2 Phillips tipped screwdriver

6. Flat pry bar
7. Soft faced mallet

CONT.

JDA 11/2000

NOTIFY EFCO IMMEDIATELY OF ANY DESCREPANCIES OR

8. Tube wax

DUE TO THE SCREW TENSIONS REQUIRED FOR CORRECT

NOTE:

INSTALLATION, IT WILL BE NECESSARY TO ’WAX’ THE FRAME
ASSEMBLY SCREWS TO PREVENT GALLING AND BREAKAGE.