Detail #29, Step #33, Step #34 – EFCO 955 Series User Manual
Page 28

1G59 STD. JAMB
glazing gasket (WMB9) with the frame laying flat. This is at the discretion of the installer.
Depending on the height of the assembled frame, it may be easier to install the exterior
Detail #31
STEP #35
Detail #30
8663 BUTT GLAZE
Butter the top ends of the jambs and vertical butt glaze mullions. Then attach the head
Detail #29
2G23
1G59 or 1G60
FRAME SILL
1G59 STD. JAMB
8663 BUTT GLAZE
2G23
2G23
VERTICAL
STEP #33
1G58 STD. HEAD
VERTICAL
REFERENCE SECTION VII
WILL BE FILLED WITH
THE K461 BRIDGE ASSEMBLY.
NOTE THE GAP BETWEEN
THE HORIZONTALS. THIS
CONT.
PAGE #26
Butter the bottom ends of the jambs and vertical butt glaze mullions. Then attach the
STEP #34
JDA 9/2000
Be sure to add approximately 2% of the cut length to prevent gaps at the gasket
intersections.
to the verticals with #STV3 screws. It will be necessary to coat the screws with
SECTION V - ASSEMBLY
wax before installation to prevent stripping. See details #29 and #30 below.
sill to the verticals with #STV3 screws. It will be necessary to coat the screws with
wax before installation to prevent stripping. See details #31 and #30 below.