Slide the FS97 head anchor into the head as shown in Detail #36 below.

into the opening and fasten as required. See details #37 and #38 above.

STEP #39

STEP #40

{FS97, FT01 & FS99 - FABRICATED PARTS}

SECTION VI - FRAME INSTALLATION

FRAME INSTALLATION INTO THE OPENING

the building. Align the sill over the sill anchors and rotate the frame

The 955 system is designed to rotate into the opening from the interior of

FS99

Detail #37

Detail #38

PAGE #29

Detail #36

VERTICALS

6" FROM

VERTICALS

6" FROM

MAX.

16" O.C.

AND 16" ON CENTER.

OFF EACH MULLION

HEAD MEMBER 6"

ANCHOR INTO THE

SLIDE THE HEAD

CONT.

FS97

FT01

INTERIOR