Series 8700 / 8800 Unitized Curtain Wall Installation Instructions - Volume 3

Section 7 - Outside 90° Corner Unit Frame Assembly : A. Mullion Subassembly

LEFT HAND

ASSEMBLY

KV10

TOP

BOTTOM

RIGHT HAND

ASSEMBLY

KV09

BOTTOM

TOP

M169 Hex
Head Bolt

FM05 Hook
Anchor

FM06 Hook

Anchor

FM07 Mullion
Anchor

1. Assemble anchor kits by screwing in the M170 set screw into the bottom of the FM07 mullion anchors until the set screw is flush with the bottom of the

anchor. (Left and Right Hand Assemblies Required)

2. Slide the FM05 or FM06 hook anchor into the FM07 mullion anchor as shown in Figure 1 and 2. See END VIEW on page 6 for part orientation.
3. For the dead load anchor, screw a M169 hex head bolt into the top of the FM07 mullion anchor, half way into the anchor so that 1 3/4” of the bolt extends

from it. See Figure 1 below. For the wind load anchor, screw a M170 socket set screw in the top of the anchor, flush with the top of FM07 as shown in
Figure 2, below.

Figure 1

Figure 2

FM07 Mullion

Anchor

BOTTOM

M170 Socket Set Screw

(Set flush with bottom of FM07)

TOP

FM05 Hook
Anchor

FM06 Hook

Anchor

FM07 Mullion
Anchor

FM07 Mullion

Anchor

M170 Socket Set Screw

(Set flush with top of FM07)

M170 Socket Set Screw

(Set flush with bottom of FM07)

LEFT HAND

ASSEMBLY

KV16

TOP

BOTTOM

RIGHT HAND

ASSEMBLY

KV15

DEAD LOAD

ANCHOR

WIND LOAD

ANCHOR