The following steps will guide you in planning and installing a PowerFlex 755
IP00, NEMA/UL Open Type drive.
1. Considerations
❏ Drive size (Hp & V AC), required accessories/options (HIM, comms, etc.)
❏ Ingress protection of system
❏ Mounting orientation of drive
❏ Cooling method, venting orientation, alignment of venting
❏ Control pod mounting location
❏ Cabling entry/exit scheme and cable routing provisions
❏ Roll-out cart required
❏ Personnel safety and necessary tooling
2. Selection
❏ Select and purchase enclosure with sub-panel and ingress accessories (page
❏ Select and purchase drive and corresponding drive options (see
)
❏ Select and purchase pod and corresponding cables (page
or page
)
❏ Select and purchase field termination kits (page
)
❏ Select and purchase appropriate mounting kits (drive mounting & floor - page
or page
❏ Select and purchase door fans (pages
…
)
❏ Select and purchase necessary wire and cabling (pages
&
3. Prepare the Enclosure
❏ Create ventilation openings, mount door fans (pages
…
❏ Provisions for accessories (HIM cradle, etc. - see
❏ Fabricate and mount inlet and outlet plenums (pages
)
❏ Drill sub-panel(s) (page
❏ Mount field termination kit, mounting brackets, and floor kit (page
)
❏ Mounting of customer specified accessories
❏ Remote mounting of control pod (if specified - see
❏ Mount sub-panel(s)
4. Power and Ground Wiring
❏ Ensure proper grounding (page
)
❏ Position & secure movable L-brackets (page
)
❏ Properly terminate power cables (page
)
5. Roll-in and Secure the Drive Unit
❏ Raise drive unit to vertical orientation (page
❏ Position roll-out cart
❏ Lift drive unit onto cart
)
❏ Roll drive unit into cabinet and secure (see
6. Control Wiring
❏ Mount control pod into drive (if specified - page
)
❏ Verify control transformer voltage (page
)
❏ Ensure proper cable routing (page
)
❏ Attach pod power and fiber optic cables (page
)
❏ Install real time clock battery and HIM cable (page
❏ Install remaining control wiring (pages
)
❏ Verify correct torque on all fasteners and connectors
7. Commission the System