6 commissioning, 1 before initial switch-on, Commissioning – Lenze E84DGFCT User Manual
Page 25: Before initial switch-on

EDS84DMOTECAT EN 2.1 - 11/2012
L
25
Communication manual 8400 motec EtherCAT®
Commissioning
Before initial switch-on
6
Commissioning
During commissioning, system-related data such as motor parameters, operating
parameters, responses, and parameters for fieldbus communication are defined for the
controller. For Lenze devices, this is done via the codes.
The codes of the controller and communication are saved non-volatilely as a data set in the
memory module.
In addition to codes for the configuration, there are codes for diagnosing and monitoring
the nodes.
The data from the controller or memory module can only be read in conjunction with the
main voltage supply (400/500 V AC).
During commissioning with 24 V DC, only the information provided by the last two data
words in the digital and analog inputs is valid and readable (see
).
6.1
Before initial switch-on
Stop!
Before the controller is switched on for the first time, the entire wiring must be
checked for completeness, short circuit and earth fault.