Final works

Initial commissioning at a mains voltage of 400 V

8

l

65

EDK94ARN24 DE/EN/FR/ES/IT 2.1

8

Final works

8.1

Initial commissioning at a mains voltage of 400 V

The regenerative power supply module can be operated at a mains voltage of 400 V after
it has been installed according to these mounting instructions.

For this purpose, regenerative feedback is activated via the digital RFR input.

How to proceed:

1. Switch−on the mains voltage of 24 V.

– for the mains filter
– for the regenerative power supply module (optional)

2. Switch−on the mains voltage of 400 V.

3. Activate/deactivate regenerative feedback via the digital RFR input.

8.2

Initial commissioning at a mains voltage of 230 or 500 V

At first, the mains voltage must be set in the regenerative power supply module for the
operation at a mains voltage of 230 or 500 V. The setting will be done in C00173 and can
be carried out using a keypad or the Lenze Engineer PC software.

Required for the commissiong:

ƒ

A EZAEBKx00xkeypad

or

ƒ

A computer with a Windows® operating system (XP or 2000)

ƒ

The Lenze Engineer PC software

ƒ

A connection to the regenerative power supply module via an interface, e.g.
– X6 diagnostic interface with USB diagnostic adapter
– CAN system bus
– Communication modules in the M1/M2 expansion slots

ƒ

The software manual for the technology application used

ƒ

The communication manual for the network of the automation platform

ƒ

Switch−on the mains voltage of 24 V.
– for the mains filter
– for the regenerative power supply module

After the setting has been carried out according to the existing mains voltage:

1. Switch−on the mains voltage.

2. Activate/deactivate regenerative feedback via the digital RFR input.