beautypg.com

Assembly and alarm verification tests – AirSep Eclipse 5 20631679 User Manual

Page 50

background image

Personal Ambulatory Oxygen System Provider Technical Manual

50

PN 20631679 Rev C

ASSEMBLy AND ALARM VERIFICATION TESTS

To ensure proper assembly and functionality of the Eclipse 5 after it has been reassembled, the following steps should be
followed.

1. Install the Power Cartridge into the Power Cartridge compartment of the Eclipse 5. Plug the AC Power Supply into the

wall outlet and connect it to the External Power Connector of the Eclipse 5.

2. Press the ON button and set the Eclipse 5 to 2 LPM. At initial start-up Eclipse 5 units light the Green, Yellow and Red

LED’s accompanied by a beep. As concentration increases to ~70%, the Red LED turns off and the Yellow and Green
remain on. When the concentration reaches normal operating range (above 85%), the Yellow LED will turn off. The
Green LED will stay lit indicating normal operation. Table 3 shows the normal start-up operating conditions for Eclipse
5 Oxygen Systems. If LED is not green within 7 minutes there may be a problem with the Eclipse 5.

Green

Indicator

Yellow

Indicator

Red Indicator

Audible

Alarm

Alarm code

Operating Condition

Off

Off

Blinking

Beeps

004

Purity < 70%

Off

Blinking

Off

Off

008

Purity between 70% and

85%

On

Off

Off

Off

000

Normal Operating Condition

3. Verify that the Power Cartridge is charging as indicated by the Power Cartridge Status Gauge is moving in waterfall

fashion (scrolling from bottom to top). If the Power Cartridge Status Gauge is not moving, verify that the Power
Cartridge is properly engaged.

4. Check the Control Panel by pressing each of the Increase/Decrease, Pulse Dose Mode and No Smoking buttons and

observe that the Eclipse 5 buttons function normally.

5. Press the Delivery Mode button and set the Eclipse 5 to the patient’s normal Pulse Dose setting. Confirm that without

breathing from the unit, after 15 seconds of no breath detected, the system changes automatically to Continuous
Flow Mode. The green Delivery Mode light is blinking fast, indicating the system is delivering a Continuous Flow. After
another 15 seconds, the system stops delivering Continuous Flow and waits 15 seconds trying to detect a breath. The
cycle continues until a breath is detected.

6. After 5 minutes of operation, block the Cannula Fitting Outlet with your finger for 2 minutes and confirm that the

visual and audible alarm occurs. Unblock the Cannula Outlet Port and let it stabilize until the alarm stops.

7. Disconnect the AC Power Supply and allow the Eclipse 5 to run for about one minute. Set the Eclipse 5 to the

patient’s normal Continuous Mode setting. Confirm that the Power Cartridge Status Gauge is illuminated and External
Power Present Indicator is off.

8. Remove the Power Cartridge and verify that the Eclipse 5 alarms and red Alarm Indicator is flashing and the alarm

sounds. After about 5 seconds, re-install the Power Cartridge and connect the AC Adapter and observe that the
Eclipse 5 automatically restarts. Confirm that the External Power Present Indicator is illuminated.

9. Turn off Eclipse 5 and unplug the AC Power Supply.

10. Record results, initial and date the Service and Maintenance Record.

11. EDAT may be utilized to record Eclipse 5 device status and dates of service.