10.

Slide the drive cage assembly fully into the server chassis and install the four screws.

11.

Install the drives ("

Installing a drive

" on page

30

).

CAUTION:

To prevent improper cooling and thermal damage, do not operate the server unless

all bays are populated with either a component or a blank.

12.

Install the access panel (on page

21

).

13.

Lock the tower bezel.

14.

Connect each power cord to the server.

15.

Connect each power cord to the power source.

16.

Power up the server (on page

19

).

Eight-bay SFF hot-plug drive cage option

To install the component:

1.

Power down the server (on page

19

).

2.

Remove all power:

a.

Disconnect each power cord from the power source.

b.

Disconnect each power cord from the server.

3.

Unlock the tower bezel ("

Unlock and open the tower bezel

" on page

20

).

4.

Remove the access panel (on page

21

).

5.

Remove all installed drives.