4.3. Pump control (Pr.1 = 1)
The application :
l
2 pump control, pump down in a wet-well, duty-assist operation
l
Alternate pump duty to reduce wear
l
4-20 mA to remote indicator
l
Loss-of-Echo indication to telemetry
l
Display actual level in meters
Pr. 1
=
1
Defines level measurement.
Pr. 2
=
2
Programme in meters, display in meters.
Pr. 3
=
5.4
Transducer to zero level = 5.4 m.
Pr. 4
=
4.5
The span over which measurement is required.
Pr. 5
=
0.5
Blanking into which the material will not rise.
Pr. 6
=
1.5
Max. rate of level change 1.5 m/min.
Pr. 8
=
2
Relay 1 control on level (normally de-energised).
Pr. 9
=
3.75
Relay 1 energises at 3.75 m to turn pump 1 on.
Pr.10
=
0.5
Relay 1 de-energises at 0.5 m to turn pump 1 off.
Pr.11
=
2
Relay 2 to control on level (normally de-energised).
Pr.12
=
4.0
Relay 2 energises at 4.00 m to turn pump 2 on.
Pr.13
=
0.75
Relay 2 de-energises at 0.75 m to turn pump 2 off.
Pr.17
=
7
Relay 4 assigned to indicate loss-of-echo to the telemetry system.
Pr.23
=
2
Switch pump 1 off on failsafe.
Pr.24
=
2
Switch pump 2 off on failsafe.
Pr.28
=
1
Analogue output to 4 mA on failsafe.
Pr.29
=
30
Failsafe delay 30 secs.
Pr.30
=
2
Analogue output to be 4-20 mA fixed to Pr.4.
Pr.51
=
2
Alternate pump duty.
Pr.78
=
Simulate the program.
0.5 (Pr.10)
5.4m
(Pr.3)
0.5m
(Pr.5)
4.5m
(Pr.4)
Stop
1
Start
1
3.75
(Pr.9)
4.00
(Pr.12)
Start
2
Stop
2
0.75
(Pr.13)