15
SAS Link and Transport Layer Test Suite v0.13
Test 7.2.2 - Connections – 2 SOAF Received
Purpose: To determine that the DUT properly handles received 2 SOAF primitives.
References:
7.2.5.11 SAS Standard
Resource Requirements: SAS Protocol Analyzer and Generator
Revision History: September 7, 2004
Test Setup: The DUT and the Testing Station are physically connected.
Test Procedure (Targets):
• The Testing Station should start and complete a Phy Reset sequence followed by an Identify sequence
with the DUT. Since the DUT is a target the Testing Station should transmit an Identify Address frame
indicating that it is an initiator.
• The Testing Station should transmit the following to the DUT
o SOAF primitive
o the first 4 dwords of an OpenAddress frame
o complete Open Address frame starting with SOAF and using the SAS address of the DUT.
• Wait for the DUT to transmit OPEN_ACCEPT and RRDY.
Observable Results:
•
Verify that the DUT responded to the received, complete Open Address frame with OPEN_ACCEPT.