25. TEST, CHECK, AND STARTUP PROCEDURES
1.
After all wiring has been landed to the logic panel, disconnect the RH/RC wire from
the panel to the equipment to prevent short cycling during preliminary test/check
procedures.
2.
Make sure that all selector switches are set in the proper positions. Refer to system
setup section in the manual.
3.
Place all zone thermostats in the OFF position.
4.
Temporarily disconnect any limit or peripheral control inputs.
5.
Set SW1 selector switch in normal operation.
6.
Set SW2 selector switch in auto changeover mode.
7.
Set SW3 selector switch in intermittent fan operation.
NOTE: Remember to set SW1, SW2, and SW3 selector switches back to desired
operation after test, check, and startup procedures are completed.
8.
Power Up Test:
Energize the logic panel transformer and confirm the following:
[ ]
On initial power-up the NORMAL operation LED begins to flash.
[ ]
All zone damper LEDs are ON (damper open indication).
9.
Zone thermostat inputs and equipment outputs test:
Using a jumper wire, confirm the following for each zone terminal:
[ ]
Jumper R and G. Push and hold time delay override button SW7.
a. Current zone damper LED ON
b. All other zone damper LEDs OFF
c. G equipment output LED ON
[ ]
Jumper R and Y. Push and hold time delay override button SW7.
a. Current zone damper LED ON
b. All other zone damper LEDs OFF
c. Y equipment output LED ON
d. G equipment output LED ON
[ ]
Jumper R and W. Push and hold time delay override button SW7.
a. Current zone damper LED ON
b. All other zone damper LEDs OFF
c. W equipment output LED ON
d. G equipment output LED ON (heat pump applications only — in conventional
heat/cool applications, the LED will not come on in heat mode).
NOTE: When the logic panel is set up for heat pump equipment, confirm that the
reversing valve O/B LED is ON in proper sequence with SW4 switch configuration.
10.
Start Up:
[ ]
Deenergize the logic panel transformer.
[ ]
Reset SW1, SW2 and SW3 back to desired operation mode.
[ ]
Reconnect any limit or peripheral control wires.
[ ]
Reconnect the equipment RC/RH wire.
[ ]
Energize both the logic panel transformer and power supply for the dampers
and thermostats.
[ ]
Activate each zone thermostat in the proper mode of operation and
adjust set points accordingly.
[ ]
Allow logic panel to sequence through initial start up time delays.
SlimZone Deluxe