6. Installation
PNEG-1095 FCDL 4.00" Corrugation Externally Stiffened Grain Bin
67
Locating Chutes
1. Starting from the first row of holes in the top
sheet, measure down the “starting distance”
for the bin.
and
2. Keep adding the required number of chutes,
making sure to leave 8" between the chute bolt
holes.
Locating Discharge Opening
1. The last bolt hole in the chute should line up
with the center of the discharge chute opening
that is to be cut.
Therefore,
you should be able to approximate an opening
by measuring 9-1/2" above and below the
last bolt hole of the chute. Mark horizontal
cut lines.
2. To find the vertical center of the chute
opening, measure over 11" to the right and
left of the chute bolt rows. Mark center point.
Then from the center point,
measure 7" on both sides and mark vertical
cut lines.
3. Cut opening where marked, make sure
corners have a minimum of 1-1/2" radius.
Figure 6Y
Figure 6Z