Veris Industries TURBO SERIES Recordal Install User Manual
Page 3

5. Because of the need to test large meters periodically to verify
their performance, it is recommended that a bypass system be
incorporated into the piping arrangement. This will also provide a
means of performing periodic cleanout and routine maintenance
without interrupting service to the customer. A test tee can be installed
downstream of the meter for field accuracy testing.
6. The Recordall
®
Turbo Series is accuracy and pressure tested
prior to shipment, therefore no field adjustments are required. As
turbine performance is directly related to the flow conditions of the
water stream entering the meter, upstream fittings and piping changes
can adversely affect flow registration. To insure valid registration and
proper performance, the following factors should be considered when
installing Recordall Turbo Series meters and Turbo Series meters with
integral strainers.
a. When installing the meter with a separate Badger Plate
Strainer or integral strainer, a minimum of five (5) pipe diameters of
straight, unobstructed pipe is recommended upstream of the meter.
For optimum protection and accuracy, this straight pipe spool piece
should be installed between the separate strainer and meter as
illustrated in Figure 1. (A minimum of ten (10) pipe diameters (minimum
of 25 pipe diameters for smallest size) of straight unobstructed pipe
is recommended upstream of a meter installed without a plate strainer.
The deletion of a strainer, however, is not recommended.) This allows
for dampening of velocity profile distortions caused by elbows, pumps,
dirt traps, etc., prior to the meter. Where spiral flows are created by
three dimensional elbows or rotary pumps, additional distance to
dampen the effect is beneficial. If a basket or Y-type strainer is utilized,
it is recommended that it be placed five (5) to ten (10) pipe diameters
prior to the meter to dampen velocity profile distortions created by this
design.
b. Do not install check valves or pressure reducing devices
upstream of the meter.
c. Valves immediately upstream of the meter should only be
fully-open gate valves. Butterfly valves are acceptable if they are five
(5) pipe diameters or more upstream from the meter. Downstream,
fully open gate or butterfly valves can be used.
d. The service saddle (or reducing tee) which is used for field
accuracy testing should be at least two (2) pipe diameters downstream
of the meter's outlet flange.
e. Unweighted check valves should not be located closer than
three (3) pipe diameters downstream of the meter.
f.
Externally weighted check valves and pressure reducing
devices should not be located closer than five (5) pipe diameters of the
meter.
g. When installing a turbo meter and plate strainer of a size
smaller than the pipe installation, to reduce the effect of jetting caused
by the increase in flow velocity, a minimum of five (5) pipe diameters
is recommended upstream of the meter. Additional length is recom-
mended if a sharp contraction or an eccentric reducer, rather than a
concentric, tapered reducer is used.
B. INSTALLING THE METER. Overall dimensions and laying lengths
of each meter size are shown on the Technical Briefs. After reviewing
the applicable dimensional requirements, choose an appropriate in-
stallation point in the piping and proceed as follows:
1. Measure precisely the overall length of the meter with gaskets
attached to the inlet and outlet flange connections.
2. Provide proper gap length in service piping.
3. Install meter in the pipeline so that the flow arrow on the meter
housing points in the same direction as water flow.
arranged to provide sufficient back pressure to maintain
a full line at the meter. By eliminating air in the line, as
well as sudden flow surges, inaccurate registration and
damage to the turbine mechanism can be avoided.
2-3. RECORDALL TRANSMITTER REGISTER OPTION
Badger Meter Recordall Transmitter Registers are designed for use
with the Recordall Turbo Series. If the meter has been purchased with
a RTR
®
, the installation guidelines as outlined in the Installation Data
Sheet should be followed.
Before proceeding with the installation, be sure that the Recordall
Transmitter Register corresponds to the meter size, and unit of
measure.
2-4. PERFORMANCE CHECKS
Any valves or devices controlling the flow of water through a turbo
meter must always be opened and closed SLOWLY to prevent shock
loads that may damage the meter's rotor assembly.
Complete the following checks to ensure that a turbo meter is properly
installed and operational:
a. Slowly open upstream valve to apply water pressure to the meter
and check to see if there are any leaks. Tighten flange bolts as
required.
b. Perform a functional test of the meter. Slowly open valve on
downstream (consumer) side of the meter to evacuate any air that may
have been trapped in the service line. When air has been eliminated,
increase demand flow rate by further opening of downstream valve or
valves. Observe register for correct direction of flow. The large test
pointer will now move in the proper direction. Now open all applicable
service valves.
c. Adjust rate of flow by throttling with the downstream valve so the
flow does not exceed the maximum continuous duty specification as
defined in the Technical Briefs. The rate of flow can be quickly checked
by timing the quantity registered through the meter in one minute.
2-5. SHUTDOWN INSTRUCTIONS
If the turbo meter is to be shut down for an extended period of time or
if it is being removed from service, Badger recommends that the meter
and measuring components be thoroughly flushed to prevent the
settling out of undissolved solids or the accumulation of corrosive
deposits. If there is an upstream strainer in the line, it also should be
flushed at this time.
Figure 1. Recommended Meter Installation
BY-PASS
(PERMANENT OR
TEMPORARY)
UPSTREAM
VALVE
(open)
MINIMUM OF FIVE
DIAMETERS OF
STRAIGHT PIPE
BADGER PLATE
STRAINER AND TURBO
SERIES METERS
COUPLING
ADAPTOR
SERVICE
SADDLE
SHUT-OFF
VALVE
DOWNSTREAM
TEST TEE
MINIMUM TWO
PIPE DIAMETERS
DOWNSTREAM
OF TURBO
METER
Page 3
meters. For use with water at higher temperatures, consult your
Badger Meter representative or nearest Badger regional sales office.
3. Installation of a strainer is recommended upstream of the meter.
The strainer, in addition to protecting the meter from debris in the line,
minimizes the effect of velocity profile distortions or turbulence caused
by changes in pipe direction or valving resulting in more accurate
registration. Contact your Badger Meter representative for informa-
tion on Badger
®
Plate Strainers.
4. Avoid locating the meter in close quarters. Allow sufficient
space to permit access for meter reading, testing, and maintenance.
4. With meter and gaskets in place, tighten flange connection bolts.
5. To relieve possible strain on the piping, it is recommended that
a meter support be used under the meter housing where appropriate.
Turbine meters must operate in a completely filled line
at all times. The downstream piping must always be