INSTALLATION AND ASSEMBLY

(1) Weight-tolerant

The ground must be flat and horizontal. It should be able to bear the weight of the system.
For wooden floors, if the part receiving the weight of the system lies at the center between the reinforcement
beams below the floor, the floor may become deformed or may curve inwards. In such cases, lay a more than 12
mm thick board below the system to distribute the weight of the system on the floor.

For concrete floors, it may not be possible to install the system horizontally due to the roughness of the floor. In
such cases, do the same as above.
After installation, adjust and secure with the floor leveler.

(2) Height to ceiling

¶ Leave about 30 cm between the top of the system and ceiling. Take note that if there are air-conditioner vents

or lights at the top, problems caused by dusts, temperature, humidity, and water drop may result. If adequate
space cannot be provided on the left and right sides, and at the back of the system, and the system is be
installed directly onto the wall, heat can only be discharged from the top. In such cases, be sure to provide
vents for discharging heat. Also observe the temperature and humidity conditions in (7).

(3) Front Space

¶ Finger and hand prints form easily on the face of the screen. Therefore make sure viewers cannot touch it

directly.

Leave workspace in front for replacing the screen.

(4) Rear Space

¶ At least 5 cm of space is required at the back of the system. However, leave more than 1 m at the back as

working space for the maintenance of the MPJ and MVP.

(5) Installation work for securing system

¶ After installation, always lower the floor levelers to prevent the system from turning over.

This system is also provided with holes to hook wires for preventing it from turning over. To prevent the
system from turning over, it is recommended that it be secured to the floor or wall.

¶ The method of securing to floors and walls differ according to their materials. Always have a construction

specialist or Pioneer dealer perform the procedure for you.