Planning / Readiness / Implementation Timelines

Planning / Readiness / Implementation Timelines

The following activity guidelines allow sufficient time for planning, readiness, and imple-
mentation tasks to be completed prior to delivery of VSM5 system equipment to a custom-
er site.

1.

Three months before the scheduled delivery date for the VSM5 system equipment:

• The network administrator, data center manager, and Sun account representative,

systems engineer (SE), and technical support specialist (TSS) define a system con-
figuration that best addresses customer requirements.

• The site engineer, facilities manager, and Sun Professional Services consultant re-

view site factors that present existing or potential safety and environmental hazards
which could negatively affect the operation of the VSM5 system. See

“Site Evalua-

tion – External Considerations”

and

“Site Evaluation – Internal Considerations”

on

page 4-46.

• The facilities manager and Sun Professional Services review equipment transfer re-

quirements and define a compliance plan as needed. See

“Transfering Equipment

Point-to-Point”

on page 4-47.

• The facilities manager and Sun Professional Services consultant review power sup-

ply and cabling requirements, and evaluate compliance to requirements. See

“Site

Power Distribution Systems”

on page 4-49.

• The site engineer, facilities manager, and structural engineer (if needed) review floor

construction and load ratings, and evaluate compliance. See

“Floor Construction Re-

quirements”

and

“Floor Loading Requirements”

on page 4-52.

• The network administrator, data center manager, and Sun technical support special-

ist review data cabling requirements for the VSM5 system configuration, and evalu-
ate compliance to requirements. See

“Fibre Channel Cables — Available Lengths”

on page B-166.

• After completing reviews of power, environmental, flooring, and network connectivity

requirements, the site engineer and facilities manager schedule needed facilities up-
grades, targeting completion for not later than one week before delivery of system
equipment (two weeks is preferable).

2.

Two months before the scheduled delivery date for the VSM5 system equipment:

• The site engineer and facilities manager create a floorplan/layout for all VSM5 sys-

tem equipment, and review it with the Sun Professional Services consultant. See

“Physical Space Requirements”

on page 4-55.

Note:

A copy of the final floorplan/layout should be given to the Sun sales represen-
tative to attach to the sales order.

• The facilities manager and Sun technical support specialist measure and record ca-

ble-layout distances between AC source power locations, host systems, network
servers, remote support devices, and VSM5 system hardware components.