Before commissioning
After the tightness check has
been successfully completed,
connect the vacuum pump via
the pressure gauge station to the
valve connections on the outdoor
component (see chapter "Tightness
check") and create a vacuum.
Perform the following checks
prior to commissioning the
unit for the first time and after
any interventions affecting the
refrigerant circuit. Record the
results in the commissioning report:
■
Check all refrigerant pipes and
valves using leak detection spray
or soapy water to ensure they
are tight and that the suction
and injection pipes are not
accidentally mixed up.
Perform this check when the
unit is not running.
■
Check the refrigerant pipes and
insulation for signs of damage.
■
Check the correct polarity of the
connection between the indoor
unit and outdoor component.
Add refrigerant
The equipment contains a basic
quantity of refrigerant.
Extra refrigerant must be added if
the basic length of the refrigerant
pipes exceeds 5 metres. Refer to
the following table:
SV
261
SV
351
SV
521
SV
681
Basic pipe
length
Additional fill quantity
Up to and incl.
5 m
-
5 m to max.
15/25 m
25
g/m
25
g/m
25
g/m
45
g/m
Commissioning
SV 261-681 AT
Colour code
WH = white
BU
= blue
BR
= brown
BK
= black
1
2
3
L
N
Liquefier fan
Compressor
Compressor
contator
Reverse flow valve
Mains cable
230V / 1~ / 50 Hz
Note that the employed refrig-
erant is always filled in liquid
form!
CAUTION
NOTE
Check the overheating to
determine the refrigerant fill
quantity.
Wear protective clothing when
handling refrigerant.
CAUTION
Commissioning should only be
performed and documented
by specially trained personnel.
NOTE
The system can be commissioned
once all the components have
been connected and tested.
A functional check should be
performed to verify its correct
function and identify any unusual
operational behaviour prior to
handing it over to the operator.
■
Check that all fastenings,
mountings etc. are firm and at
the correct level.