5.1 Start-up Checklist
•
Confirm that power is correctly connected to the display.
•
Allow for sufficient power as listed in the display Shop Drawing and Power Specs.
•
Assure a main disconnect switch is used to control power.
•
Inspect all circuit breakers (internal and external) for sufficient marking and size.
•
Confirm that adequate grounding is installed. Each display face must have a separate
earth-ground conductor with a resistance of 10 Ohms or less.
•
Assure the external communication equipment (signal enclosure, client radio, etc.) is
properly installed.
•
Inspect signal connections at the control computer.
•
Inspect signal connections at the display.
Inspect signal connections between displays when necessary.
•
Confirm that the control computer is correctly configured.
Follow the step-by-step directions in the Venus
®
1500 Help File’s Configuration
section for correct setup.
•
Inspect peripheral equipment (temperature sensor, etc.) for proper installation.