Start-up Procedure

19

Section 5:

Start-up Procedure

Before starting the display, review the following list. Figure 3 shows the basic display components

referred to in each step.

5.1 Start-up Checklist

Confirm that power is correctly connected to the display.

Allow for sufficient power as listed in the display Shop Drawing and Power Specs.

Assure a main disconnect switch is used to control power.

Inspect all circuit breakers (internal and external) for sufficient marking and size.

Confirm that adequate grounding is installed. Each display face must have a separate

earth-ground conductor with a resistance of 10 Ohms or less.

Assure the external communication equipment (signal enclosure, client radio, etc.) is

properly installed.

Inspect signal connections at the control computer.

Inspect signal connections at the display.

Inspect signal connections between displays when necessary.

Confirm that the control computer is correctly configured.

Follow the step-by-step directions in the Venus

®

1500 Help File’s Configuration

section for correct setup.

Inspect peripheral equipment (temperature sensor, etc.) for proper installation.