Connecting the fryer to the gas supply, Moving the fryer – Belshaw Adamatic Mark II-Gas Donut Robot User Manual
Page 47
Belshaw Bros., Inc.
• www.belshaw.com • Phone 206-322-5474 • Fax 206-322-5425
Donut Robot Mark II-Gas TS
MN-1018EN
7
Connecting the Fryer to the
Gas Supply
1. Ask your local gas company to advise you
on the size of pipe and gas meter you should
use.
2. Connect the fryer to the building’s gas
supply.
3. Seal all threaded joints between gas pipes
with pipe joint compound. You must use a
compound that resists the action of liquefied
petroleum (LP) gases.
4. Bleed the gas lines of all air.
5. Check all gas connections and fittings for
leaks using a gas leak detector, a soap
solution, or a similar substance. When such
a substance is applied to connections and
fittings, bubbles indicate gas leaks.
Moving the Fryer
If you ever want to move the fryer to a different
workstation, follow this procedure:
1. Turn off the machine and disconnect it from
the power source. Unplug the cutter head
power cord.
2. Turn off the gas supply. Disconnect the
machine from the gas supply.
3. Allow the machine and the shortening to
cool.
WARNING
Do not touch hot shortening. It can cause
serious burns.
4. Remove and set aside the plunger, the
hopper, and the cutter head, in that order.
5. Disconnect the swing connecting rod.
6. Remove the shortening from the fryer as
explained in “Removing the Shortening” in
Section 2 of the Operator's Manual.
7. To avoid dropping the machine or getting
shortening on the floor, wipe excess
shortening off of the fryer and the conveyor.
WARNING
Thoroughly clean and dry the floor if
shortening is spilled. Materials on the floor
can cause people to slip or fall, resulting in
serious injury or loss of life.
8. Set aside the conveyor.
9. Remove the nuts and bolts that hold the
control box in place. Remove the control
box from the fryer.
10. To prevent tripping, coil the power cord.
Move the control box to the new work
station.
11. Move the fryer to its new location.
12. Install the control box.
13. Move and install the conveyor.
14 Move and install the swing column.
Connect the swing connecting rod.
15. To prevent tripping, coil the cutter head
power cord. Move and install the cutter
head.
16. Move and install the hopper and the plunger.
17. Level and secure the fryer.
18. Connect the fryer to the building’s gas
supply, and seal all pipe joints with joint
compound.