Initial Cleaning

Thoroughly clean your Donut Robot Mark II-Gas
before using it. Refer to Section 3, “Cleaning,”
for cleaning instructions.

WARNING

To avoid electrocuting yourself or

damaging the machine, never allow water,
steam, cleaning solution, or other liquid to

enter the cutter head or the control box.

WARNING

Never let water and hot shortening come in

contact with each other. Moisture causes

hot shortening to spatter, which may cause

serious injury. Prior to use, make sure the

kettle and any other parts you have washed

are dry.

Assembling the Fryer

1. Place the fryer case on a flat, stationary

surface.

2. Screw the fryer’s legs in as far as they will

go.

3. Set the kettle into the fryer case. The end of

the kettle that has the locating pin must be
placed at the outfeed end of the fryer case.
The lip of the kettle should fit securely over
the edge of the case.

4. Install the control box as follows:

a. Align the holes in the control box

mounting flanges with the holes in the
mounting brackets.

b. Slide the bolts through the holes.

c. Tighten the nuts onto the bolts.

5. Lower the control box assembly into

position so the thermostat bulb bracket rests
on or very near the bottom of the kettle.

6. Install the conveyor assembly as follows:

a. Hold the conveyor at the angle shown in

Figure 1-2 and slide the conveyor drive
coupling over the main drive shaft
coupling. The conveyor coupling has a
notch in it. Turn the conveyor coupling
until the head of the socket head screw
in the drive coupling can slide into this
notch. (See Figure 1-2.)

b. Lower the front side of the conveyor

assembly so the hole in the conveyor
flange fits over the locating pin on the
lip of the kettle.

Figure 1-2. Joining the Couplings.

If you are preparing to make yeast-raised donuts,
skip steps 7 and 8 and proceed to step 9.

7. Insert the swing column into the swing

column mounting bracket. Make sure the
plastic spacer washer is on the swing column
between the set collar and the swing column