Installation, Packing list, Additional items required – Avalon Firestyles Bed & Breakfast Installation User Manual
Page 7: Recommended installation procedure

Installation
(for qualified installers only)
7
Travis Industries
4140312
100-01305
Packing List
Propane Conversion Kit (Orifices, Rivet)
Log
Set
Firestop
(sku
93006094)
Rear Vent Configuration Kit (insulation)
(4) AA Batteries, (1) 9-Volt Battery
Felt Tabs (for concealment cover)
Remote
Control
Additional Items Required
If using LP (propane) a conversion kit is required (sku 94400999 – GSR Stepper Motor Kit).
Direct
Vent
Gas Line Equipment (shutoff valve, pipe, etc.)
Electrical Equipment (min. 14 gauge, grounded line)
Recommended Installation Procedure
HINT:
We strongly recommend installing all of the optional equipment before placing the fireplace.
Place the fireplace on a suitable work stand to ease installation.
Install the optional equipment (do not install the logs) – we recommend the following order:
a) LP Conversion (if applicable) – NOTE: leave the burner removed until after the liner is
installed (if applicable). If using the GreenSmart remote, install the modulating regulator
during LP conversion.
b) Liner (if applicable) – NOTE: You will need to loosen the accent light bracket while installing
the liner (see page 50).
c) Blower
NOTE: Do not install the rheostat if using the GreenSmart remote.
e) Remote
Frame the opening for the fireplace. Make sure to allow for vent installation.
This fireplace is designed to accommodate 1/2" drywall or 1/2” drywall with 3/8” tile (see "Nailing
Brackets" on page 17 for details). Secure the fireplace to the framing.
NOTE: If the facing is not 1/2" or 7/8" thick, follow the directions below:
Place a strip of facing material to both sides of the fireplace opening (NOTE: the strips will be
removed after the fireplace is secured). The facing thickness must represent the total thickness
of the finished facing (e.g.: If tile is to be used, include the thickness of the backboard, tile, and
tile adhesive). Insert the fireplace into the framing. Slide it back until the front edge of the
fireplace is flush with the facing material. Secure the fireplace using the plates located along the
base of the fireplace.
Complete the gas line installation. Complete the electrical hook-up.
Complete the vent installation.
Install the hearth (if applicable).
Install the drywall and facing (if applicable).
Install the mantel (if applicable).
Finalize the installation (see page 38) and install the grill or face.