beautypg.com

3 connecting the module, 4 function test during commissioning, Connecting the module – Pilz PSSu E F 2DO 2 User Manual

Page 27: Function test during commissioning

background image

Wiring

Operating Manual PSSu E F 2DO 2(­T)(­R)
21322­EN­05

27

6.3

Connecting the module

Output circuit

Without C­rail

With C­rail

Single­channel actuator

21

11

22

12

23

13

24

14

0 V

O0

O1

0 V

n.c.

n.c.

0 V

0 V

21

11

22

12

23

13

24

14

0 V

O0

n.c.

O1

n.c.

0 V

Dual­channel operation

Redundant actuator

With feedback loop

21

11

22

12

23

13

24

14

0 V

O0

n.c.

O1

n.c.

0 V

K1

K2

T0

T0

T1

I0

I1

I3

21

11

22

12

23

13

24

14

PSSu E F 4DI

K1

K2

RFK

PSSu E F 2DO 2

0 V

0 V

21

11

22

12

24

14

0 V

O0

n.c.

O1

n.c.

0 V

23

13

K1

K2

PSSu E F 2DO 2

T0

T0

T1

I0

I1

I3

21

11

22

12

23

13

24

14

PSSu E F 4DI

K1

K2

T1

I2

RFK

6.4

Function test during commissioning

An error must be simulated for each safety­related output during commissioning: The anti­
cipated error reaction must occur when an output has a short circuit to a supply voltage.