Commissioning check list, General, Unit - ducted evaporative air conditioner – Bonaire LV User Manual
Page 36: Unit – ducted heating

Multi-Appliance Manual Control
Controls – Installation / Setup / Commissioning
COMMISSIONING CHECK LIST
G
ENERAL
All equipment ordered by the customer is installed.
The unit is level and secure.
The mains and control wiring are complete and the circuit breaker and GPO are turned ON.
All Controller functions for the appliance operate.
All electrical or gas connections are to manufacturers specifications and the relevant electrical
or gas standards and codes.
U
NIT
-
D
UCTED
E
VAPORATIVE
A
IR
C
ONDITIONER
The water supply line has been flushed to clear swarf and debris and is free of leaks.
The tank is free of foreign matter and debris and the water isolating tap is turned ON.
Water drainpipe work is completed and sealed.
The water basin fills with water and the float valve closes correctly when the water level is 65-
70mm below the overflow level.
The water pump operates correctly when turned ON at the controller.
The Dialflo water bleed rate is adjusted to suit local water conditions.
The Superclean Dump Valve (option). The tank drains correctly when unit turns off.
The fan deck is correctly located and the fan blade spins freely.
The fan operates through the entire speed range.
The minimum fan speed is correctly set.
Water distribution is even with the filter pads fitted and the air conditioner operating pump and
fan.
U
NIT
–
D
UCTED
H
EATING
Electrical polarity of the power outlet is correct.
Heater is installed away from sources of dust and fumes (i.e. pool chlorine/petrol etc).
Gas leaks checked for, none present.
Flue outlet pipe complies with limits given / code and is sealed waterproof.
Combustion air meets requirements (internal, under floor).
Bonaire Control Systems
Page 36