INSTALLATION

2-5

CONDENSATE

TRAP

CONNECTING

MANIFOLD

DRAIN

PIPE

3/4" NPT

NIPPLES

TO

FLOOR

DRAIN

CLAMP

1" I.D.

HOSE

ADAPTOR

Figure 2-6

Condensate Trap Installation

2.7 GAS SUPPLY PIPING

The AERCO

Benchmark 3.0

Gas Components

and Supply Design Guide, GF-3030 must be

consulted prior to designing or installing any gas

supply piping.

WARNING

NEVER USE MATCHES, CANDLES,

FLAMES OR OTHER SOURCES OF

IGNITION TO CHECK FOR GAS

LEAKS

.

CAUTION

Many soaps used for gas pipe leak

testing are corrosive to metals. There-

fore, piping must be rinsed thoroughly

with clean water after leak checks

have been completed.

All gas piping must be arranged so that it

does not interfere with removal of any

covers, inhibit service/maintenance, or

restrict access between the unit and

walls, or another unit.

Benchmark 3.0 Dual-Fuel units contain two 2

inch gas inlet connections on the rear of the unit

as shown in Figure 2-4. If one of the fuel

sources is not being piped due to its

unavailability, the inlet must be capped.
Prior to installation, all pipes should be de-

burred and internally cleared of any scale, metal

chips or other foreign particles. Do Not install

any flexible connectors or unapproved gas

fittings. Piping must be supported from the floor,

ceiling or walls only and must not be supported

by the unit.
A suitable piping compound, approved for use

with natural gas, should be used. Any excess

must be wiped off to prevent clogging of

components.
To avoid unit damage when pressure testing gas

piping, isolate the unit from the gas supply

piping. At no time should the gas pressure

applied to the unit exceed 2 psi. Leak test all

external piping thoroughly using a soap and

water solution or suitable equivalent. The gas

piping used must meet all applicable codes.

2.7.1 Gas Supply Specifications

The gas supply input specifications to the unit

for Natural Gas and Propane are as follows:

Natural Gas - The maximum static pressure

to the unit must not exceed 2 psi. The gas

supply pressure to the unit must be of

sufficient capacity to provide 3000 cfh while

maintaining the gas pressure at 5.7" W.C. for

FM gas trains, or 6.5" W.C. for IRI gas trains.

Propane - The maximum static pressure to

the unit must not exceed 2 psi. The gas

supply pressure to the unit must be of

sufficient capacity to provide 1200 cfh while

maintaining the gas pressure at 3.5" W.C. for

FM or IRI gas trains.

2.7.2 Manual Gas Shutoff Valve

Two manual shut-off valves must be installed in

the gas supply lines upstream of the Boiler as

shown in Figure 2-7. Maximum allowable gas

pressure to the Boiler for each line is 2 psi.