beautypg.com

Aintenance, Verview, Reventative – Conair SC-5 User Manual

Page 70: Chedule

background image

This section describes the daily, weekly, monthly and semi-
annual maintenance schedules that should be performed when
changing materials or lines, or when changing equipment, as
well as the maintenance procedures to follow.

Cutting either flexible or rigid materials generates tremendous
shock and vibration to the entire unit. Anything that can
loosen, will over time.

To maintain the best performance, follow this maintenance
schedule and develop an effective preventative maintenance
program.

Daily

Checking cutter blade(s)

Clean, sharpen or replace as needed (see Checking the
Blades, Section 5
).

Inspecting the blade mounting hardware

The blade securing bolt should use both a lock washer
and flat washer, and be tightened enough to fully com-
press the lock washer. Replace the holding pins if they
appear worn.

Inspecting the cutter bushing screws

Check that the cutter bushing screws are secure (see
Inspecting Cutter Bushing Screws, Section 5).

Checking the closure latch on the knife guard

See Checking the Closure Latch, Section 5.

Inspecting cutter alignment

Proper cutter alignment is critical for optimum perfor-
mance. Use a plumb line or laser to check for a
straight line from the extrusion die to the cutter bush-
ings.

Check floor locks

It is always recommended that the weight be removed
from the casters for optimum stability during cutting
cycles. Check to see if the floor locking mechanism is
properly adjusted.

SC-5 SURE CUT Servo Knife Cutter

UGE059/1003

5-4

M

AINTENANCE

M

AINTENANCE

O

VERVIEW

P

REVENTATIVE

M

AINTENANCE

S

CHEDULE

Continued