ASSEMBLE THE ERV ROOF CURB — Connect the curb

side and the curb end. Insert the tabs on the curb end into the

slots on the curb sides. See Fig. 6. Press firmly until the pieces

lock into place. It may be necessary to exert additional force on

top of the curb to lock the pieces in place. Ensure the curb piec-

es are locked together prior to proceeding further. Repeat for

other corners of the roof curb.
NOTE: If lifting or moving the roof curb assembly, hammer

the tabs over 90 degrees.
PREPARE ROOF CURB LOCATION — Cut a hole in the

roof for duct openings. See Fig. 7 for duct opening dimensions.

Frame the opening to provide adequate structural support.
SET THE ERV ROOF CURB — Fit the roof curb assembly

by measuring across the corners of the curb to ensure a square

fit. Set the roof curb over the roof opening. Level the curb by

placing shims under the bottom flange of the curb. Secure the

curb in place by welding or fastening the curb to the roof.
INSTALL DUCTWORK — Ductwork will be installed in the

ERV roof curb for applications utilizing the drop-in damper

box. The duct will hang from the top of the curb. Refer to

Fig. 7 to determine the duct size required. Provide field-

manufactured duct and place into the supply and return open-

ings in the curb.
NOTE: Ductwork must be installed in the ERV curb before the

ERV unit is set in place.
NOTE: Drop-in damper box must be installed in the RTU curb

before the RTU is set in place.
INSTALL GASKETS — The ERV roof curbs come with a

gasketing package to provide a seal between the ERV unit and

the top perimeter of the roof curb. Install the gasket around the

top perimeter of the curb and around the supply and return

opening. Gasket strips must fit tightly together, leaving no gaps

for leakage.

INSTALL ROOFING MATERIALS — Insulate and add a

cant strip to the roof curb. Follow suggested and acceptable

roofing procedures for applying roofing materials. The roofing

material should extend up to the wood nailer and be secured

under the counter flashing. Follow all local, national, and in-

dustry roofing standards. Refer to Fig. 4 for roofing recommen-

dations.
INSTALL DROP-IN DAMPER BOX — Place the damper

box into the RTU curb. Allow the damper box flanges to rest

on the curb. Secure the damper box in place with 1-in. self-tap-

ping screws. Install ductwork to connect the damper box to the

ERV curb. The upper damper box connection must be ducted

to the ERV supply air, and the lower damper box connection

must be ducted to the ERV exhaust air. See Fig 5. Refer to the

drop-in damper box dimensional sheets to determine the duct

size required. Your local Carrier sales representative can pro-

vide you with this dimensional data.

Step 4 — Install Horizontal Base and Transi-
tion (62EB-EU and 62E2-E7 Units) —

The hori-

zontal transition accessory is used to connect the ERV to the

horizontal return of a Carrier rooftop unit. To provide horizon-

tal exhaust and ventilation air connections on 62EB-EU units,

the horizontal base accessory must also be installed. The acces-

sory is not needed on 62E2-E7 units. The rooftop unit must be

installed on a standard 14 in. high roof curb and positioned at a

specific distance relative to the ERV base. A typical arrange-

ment is shown in Fig. 8 and 9. See Fig. 10 for 62E2-E7 unit di-

mensions. Your local Carrier sales representative can provide

you with dimensional data for the appropriate Carrier RTU and

62E model installation.
LOCATE THE ROOF CURB — Prior to locating the roof

curb consider the structural support required for the rooftop

system. Allow sufficient space for service, clearance, and loca-

tions of vent or other sources of air. Refer to Fig. 2, 3, and 10

for ERV clearance requirements. Refer to the rooftop installa-

tion instructions for more information regarding location

considerations.

Proper location of the roof curb in relationship to the RTU

roof curb is critical for proper fit of the horizontal transition.

See Fig. 8 and 9. Refer to the ERV unit submittals provided by

your local Carrier sales representative for the correct

dimensions.

IMPORTANT: Gasket installation is critical for water

integrity. Improperly installed gaskets can result in air or

water leaks, leading to poor unit performance.

Fig. 1 — Typical Combination Curb

LEGEND

NOTES:

1. Return air ductwork sits 12 in. below bottom of

curb. (Stub duct provided.)

2. Dimensions shown in inches.

ERV

Energy Recovery Ventilator

RTU