ASSEMBLE THE ROOF CURB — Connect the curb side

and the curb end. Insert the tabs on the curb end into the slots

on the curb sides. See Fig 6. Press firmly until the pieces lock

in to place. It may be necessary to exert additional force to the

top of the curb to lock the pieces in place. Ensure the curb piec-

es are locked together prior to proceeding. Repeat for other cor-

ners of the roof curb. See Fig. 7 and 11 for roof curb dimen-

sions.
NOTE: If lifting or moving the roof curb assembly hammer

the tabs over 90 degrees.
SET THE ROOF CURB — Fit the roof curb assembly by

measuring across the corners of the curb to ensure a square fit.

Level the curb by placing shims under the bottom flange of the

curb. Secure the curb in place by welding or fastening the curb

to the roof.
INSTALL ROOFING MATERIALS — Insulate and add a

cant strip to the roof curb. Follow suggested and acceptable

roofing procedures for applying roofing materials. The roofing

material should extend up to the wood nailer and be secured

under the counter flashing. Follow all local, national, and in-

dustry roofing standards. Refer to Fig. 4 for roofing recommen-

dations.
INSTALL THE HORIZONTAL BASE (62EB-EU UNITS

ONLY) — Remove the fork pockets from the bottom of the

horizontal base. After removing the fork pockets from the bot-

tom of the horizontal base place the base on the roof curb. Se-

cure the horizontal base to the curb using no. 14, 2-in. self-tap-

ping sheet metal screws.

Apply the factory provided gasketing material to the top

of the horizontal base. Follow the rigging directions in the

Step 6 — Rig and Place Unit section to place the ERV on the

horizontal base. Position the ERV so that the ERV's LCD dis-

play is on the opposite side of the horizontal base's duct open-

ings. Secure the ERV to the horizontal base using 1-in. self-tap-

ping sheet metal screws every 18 in. around the perimeter.
NOTE: The ERV may also be mounted to the horizontal base

prior to being set on the roof curb.
INSTALL THE HORIZONTAL TRANSITION — Apply

the factory-provided gasketing material to the horizontal transi-

tion at all points where duct connections are made. Attach the

horizontal transition to the horizontal base (62EB-EU units) or

the ERV (62E2-E7 units) and RTU return connection using

1-in. self-tapping sheet metal screws. Ensure that all connec-

tions are water and air tight.

Step 5 — Install Standard Roof Curb

VERTICAL STAND-ALONE APPLICATIONS (62EB-

EU UNITS) — The ERV unit can be installed without being

coupled with a RTU. The ERV units can be installed in one of

two stand-alone applications: vertical discharge or horizontal

discharge. Vertical discharge requires the use of a standard roof

curb. When installing a stand-alone ERV in a vertical applica-

tion complete the following steps:
Locate the Roof Curb — Prior to locating the roof curb

consider the structural support required for the rooftop system

and, the duct drop location in relation to the joists. Allow suffi-

cient space for service, clearance, and locations of vents or

other sources of air. Refer to Fig. 2 and 3 for ERV clearance

requirements.
Assemble the Roof Curb — Connect the curb side and the

curb end. Insert the tabs on the curb end into the slots on the

curb sides. See Fig. 6. Press firmly until the pieces lock into

place. It may be necessary to exert additional force to the top of

the curb to lock the pieces in place. Ensure the curb pieces are

locked together prior to proceeding. Repeat for all corners of

the roof curb.
Prepare Roof Curb Location — Cut a hole in the roof for duct

openings. See Fig. 7 for duct opening dimensions. Frame the

opening to provide adequate structural support.

Set the Roof Curb — Fit the roof curb assembly by measuring

across the corners of the curb to ensure a square fit. Set the roof

curb over the roof opening. Level the curb by placing shims

under the bottom flange of the curb. Secure the curb in place by

welding or fastening the curb to the roof.
Install Ductwork — Ductwork will be installed in the roof

curb for vertical discharge stand-alone applications. The duct

will hang from the top of the curb. Refer to Fig. 7 to determine

the duct size required. Provide field manufactured duct and

place into the supply and return openings in the curb.
NOTE: Ductwork must be installed in the ERV curb before the

ERV unit is set in place.
Install Gaskets — The ERV roof curbs come with a gasketing

package to provide a seal between the ERV unit and the top pe-

rimeter of the roof curb. Install the gasket around the top pe-

rimeter of the curb and around the supply and return opening.
Install Roofing Materials — Insulate and add a cant strip to

the roof curb. Follow suggested and acceptable roofing

practices for applying roofing materials. The roofing material

should extend up to the wood nailer and be secured under the

counterflashing. Follow all local, national, and industry roofing

standards. Refer to Fig. 4 for roofing recommendations.
HORIZONTAL STAND-ALONE APPLICATIONS (62EB-

EU and 62E2-E7 Units) — The ERV unit can be installed

without being coupled with a RTU. The ERV units can be in-

stalled in one of two stand-alone applications: vertical dis-

charge or horizontal discharge. Horizontal discharge with a

62EB-EU units requires the use of the horizontal base accesso-

ry. The horizontal base accessory include a horizontal dis-

charge box and a roof curb to support the box. The horizontal

base accessory is not required with 62E2-E7 units.
When installing a stand-alone ERV in a horizontal applica-

tion complete the following steps:
Locate the Roof Curb — Prior to locating the roof curb con-

sider the structural support required for the rooftop system. Al-

low sufficient space for service, clearance, and locations of

vents or other sources of air. Refer to Fig. 2, 3, and 10 for ERV

clearance requirements.
Assemble the Roof Curb — Connect the curb side and the

curb end. Insert the tabs on the curb end into the slots on the

curb sides. See Fig 6. Press firmly until the pieces lock into

place. It may be necessary to exert additional force on top of

the curb to lock the pieces in place. Ensure the curb pieces are

locked together prior to proceeding further. Repeat for other

corners of the roof curb. See Fig. 7 and 11 for roof curb dimen-

sions.
NOTE: If lifting or moving the roof curb assembly, hammer

the tabs over 90 degrees.
Set the Roof Curb — Fit the roof curb assembly by measuring

across the corners of the curb to ensure a square fit. Level the

curb by placing shims under the bottom flange of the curb. Se-

cure the curb in place by welding or fastening the curb to the

roof.
Install Roofing Materials — Insulate and add a cant strip to

the roof curb. Follow suggested and acceptable roofing proce-

dures for applying roofing materials. The roofing material

should extend up to the wood nailer and be secured under the

counter flashing. Follow all local, national, and industry roof-

ing standards. Refer to Fig. 4 for roofing recommendations.
Install the Horizontal Base (62EB-EU Units Only) — Re-

move the fork pockets from the bottom of the horizontal base.

After removing the fork pockets, place the base on the roof

curb. Secure the horizontal base to the curb using no. 14, 2-in.

self-tapping sheet metal screws.