Setting the Fill Time for a Mainline
1. On the FlowStation, press the Flow Setup button. The Flow Setup screen displays.
2. Press the button to highlight the Main Line Setup option, and then press the OK button to
select it. The Main Line Setup screen displays.
3. Press the button to highlight the mainline that you want to set the fill time for, and then
press the OK button to select it. The Main
Line # screen displays.
6. Press the button to highlight the Fill Time
option, and then press the OK button to
select it. The Fill Time screen for the mainline
displays.
7. Press the + button to change the time in the
Fill Time field.
Setting Up Shared Flow Programs
The user selects which programs must get their water from the FlowStation.
Note: Refer to Assigning Programs to the FlowStation on page 9.
1. On the FlowStation, press the Program Setup button. The Program Setup screen displays the
list of the BaseStation 3200 controllers that have been assigned to the FlowStation.
2. Press the or button to highlight the
controller that has the program that you
want to set up, and then press the OK button.
The Program Setup screen displays.
3. Press the PRG button on the display panel to
select the program that you want to work
with. The controller number and program
number display in the upper-left corner of the
screen.
Example: Cn 1, Pr 1 = Controller 1 and Program 1
4. In the Priority field, press the + or – button to change the priority for this program.
The priority settings are 1 through 10 where 1 (the default setting) is the highest priority. The
priority setting on the FlowStation controls how water is allocated to controllers and
programs, and the program priority setting on the BaseStation 3200 manages the sequence
for program starts. The priority setting on the FlowStation takes precedence over the setting
on the controller, so a program that has high priority in the controller might be scheduled to
start, but if it has low priority in the FlowStation, it might not be allocated the water that it
needs to run.
Note: For most shared flow scenarios, we recommend that you leave the Priority for all
programs set to the default (1) on the FlowStation.