Assigning programs to the flowstation, Assigning booster pumps to the flowstation, E 9) – Baseline Systems FlowStation User Manual
Page 13

Baseline FlowStation User Manual
Assigning Programs to the FlowStation
1. On the BaseStation 3200 irrigation controller, turn the dial to the Flow position.
2. Press the Next button to highlight the Assign Programs to Mainlines option.
3. Press the Enter button. The Progs to Mainline
screen displays.
4. In the Program column, press the + or –
button to select the program that you want to
assign to the FlowStation.
5. Press the Next button to move to the
Mainline column.
6. Press the + or – button to display FlowStn in
the Mainline column.
Assigning Booster Pumps to the FlowStation
Note: The pump device that you want to assign to the FlowStation must be assigned to a master
valve slot in the BaseStation 3200 before you can assign it to the FlowStation. Refer to Searching
for and Assigning Pump Start Devices and Master Valves in the BaseStation 3200 User Manual.
1. On the BaseStation 3200 irrigation controller, turn the dial to the Water Sources position.
2. Press the Next button to highlight the
Booster Pumps Program Setup option.
3. Press the Enter button. The Booster Pumps
screen displays.
4. In the Decoder field, press the + or – button
to display the master valve slot where the
booster pump device is assigned. The serial
number of the device displays next to the
field.
5. In the Use As Booster Pump field, press the +
button until FlowStn displays.
3 – Configuring the BaseStation 3200 Irrigation Controller for Shared Flow
Page 9