beautypg.com

Enabling/disabling an assigned booster pump – Baseline Systems FlowStation User Manual

Page 19

background image

Baseline FlowStation User Manual

2. Press the  button to highlight the Booster Pump option, and then press the OK button to

select it. The Booster Pump menu displays.

3. If the Device Assignment option is

highlighted, press the OK button to select it.

If Device Assignment is not highlighted, press

the  or  button to highlight it, and then

press the OK button. The Booster Pump

Assignment screen displays.

4. When the FlowStation finds the booster

pumps, their serial numbers display in the

Action column.

5. Press the  or  button to move through the list of booster pumps in the Action column.

Highlight the serial number of the booster pump that you want to assign to the shared flow

group.

6. Press the  button to move to the Booster Pump column.

7. Press the  or  button to move through the list of booster pumps. Highlight the number

that you want to assign the booster pump to.

8. Press the OK button to select the highlighted booster pump number. The serial number of the

booster pump that you selected in the Action column now displays next to the number in the

Booster Pump column.

Note: The next serial number in the Action column is automatically highlighted. Press the 

or  button in the Booster Pump column to move to the next zone that you want to assign,

and then press the OK button.

9. Continue until you have assigned all your booster pumps to the shared flow group.

Enabling/Disabling an Assigned Booster Pump

1. On the FlowStation, press the Search & Assign button. The Assign menu displays.

2. Press the  button to highlight the Booster Pump option, and then press the OK button to

select it. The Booster Pump menu displays.

3. Press the  button to highlight the Device Setup option, and then press the OK button to

select it. The Booster Device Setup screen displays.

4. In the first column, press the + or button to select the number of the booster pump that you

want to enable or disable.

5. Press the  button to move to the Enabled field. A checkmark in the field means that the

booster pump is enabled in the FlowStation. A blank field means that the booster pump is

disabled. To change the setting, press the OK button.

4 – Configuring the FlowStation