Field operation – Great Plains YP825A Operator Manual User Manual
Page 51
Great Plains Manufacturing, Inc.
Operating Instructions
47
2014-08-15
401-651M
Field Operation
Perform all steps in “Pre-Start Checklist” on page 21
and “Field Set-Up Checklists” on page 45.
Consult seed monitor for alarms during planting. Check
that reported rates are consistent with your plan.
When reloading seed and fertilizer, check consumption
against anticipated use to that point.
First Pass Operation Checklist
Page
1.
Prime fertilizer system.
2.
Slide gates open. Shutters set.
3.
Raise planter and line up at start of first
planting row.
4.
Prime meters with seed.
Leave fan running.
5.
Unfold marker on next-row side.
6.
Pull forward, lower planter, and begin
planting for a short distance.
7.
Stop. Assess:
• planting depth
• seed spacing
• press wheel operation
• fertilizer application (if in use)
-
8.
Make necessary adjustments
9.
Resume planting.
-
Sharp Field Turns
a
Checklist
a. Monitor manifold pressure during end-of-pass
operations and turns. Adjust operations as needed
to maintain meter pressurization.
Page
1.
Fold marker
2.
Raise planter when fold is complete
3.
Make turn
4.
Lower planter
5.
Unfold marker on next-row side.
6.
Resume planting.
Suspending Planting Checklist
Page
1.
Stop tractor
-
2.
Fan hydraulic circuit to Float or Neutral
40
3.
Hydraulic drive circuit to Float or Neutral
-
4.
Fold Marker
5.
Raise planter
Ending Planting Checklist
Page
1.
Suspend operations as above, then
2.
Install transport locks
23
3.
Lights ON
-
4.
Transport