Drive side bus-bar kit installation – Rockwell Automation 20G PowerFlex 750-Series Power Option Cabinets User Manual
Page 24
24
Rockwell Automation Publication 750-IN030B-EN-P - October 2014
PowerFlex 750-Series Power Option Cabinets
Drive Side Bus-bar Kit
Installation
Installation of drive side bus-bar kits is performed after the cabinets are joined
and in their final position.
One kit is required for each phase.
Table 21 - 20-750-PBAY-RHBB-975, -1235, -1625, -2437 Kit Contents
1. Assemble the M10 carriage bolts and clamp plates.
2. Slide the carriage bolt assemblies into the cannel of the drive’s extruded
bus-bar.
3. Pass the drive side bus-bar through the access opening.
Modify Barrier Panels for Bus-bar or Wire Passage on page 18
4. Align the four bolts on the side bus-bar.
Description
Part No.
Quantity
Used with Bus-bar Kit No.
Drive Side Bus-bar
–
1
All
M10 x 45 mm Carriage Bolt
29220-903-02
4
20-750-PBAY-RHBB-975, -1235, and -1625
M10 x 50 mm Carriage Bolt
29220-903-03
4
20-750-PBAY-RHBB-2437
Bus-bar Clamp Plate
PN-37764
4
All
M10 Nut with Washer
29355-002-01
4
All
M8 x 30 mm Cap Screw
419062-5HKN
2
20-750-PBAY-RHBB-1235
M8 x 35 mm Cap Screw
419062-5HKP
2
20-750-PBAY-RHBB-975 and -1625
M8 x 40 mm Cap Screw
419062-5HKQ
2
20-750-PBAY-RHBB-2437
M8 Flat Washer
419064-1SK
2
All
M8 Lock Washer
29309-011-01
2
All
M8 Flange Nut
419063-201SK
2
All
IMPORTANT
Verify that clamp fits squarely in the bus-bar slot.