11. Install fire stops where vent passes through floors,

ceilings or framed walls. The fire stop must close

the opening between the vent pipe and the structure.

Fire stop manufacturers are Air-Jet, American Metal

Products, Metal-Fab, and Simpson Dura-Vent.

12. Whenever possible install vent straight through roof.

Refer to Figure 6. Maintain minimum clearance to

combustible materials. For attic offset see Figure 7.

13.

Install Vent Terminal.

a. Size roof opening to maintain minimum

clearance from combustible materials.

b. Use appropriately designed vent flashing

when passing through roofs. Follow flashing

manufacturers’ instructions for installation

procedures. Flashing manufacturers are Air-

Jet, American Metal Products, Metal Fab, and

Simpson Dura-Vent.

c. Extend vent pipe to maintain minimum vertical

and horizontal distance of twelve (12) inches

from roof surface. Allow additional vertical

distance for expected snow accumulation.

Provide brace as required. Refer to Figure 15.

d. Vertical venting requires flashing and a storm

collar to prevent moisture from entering the

structure.

e. Install storm collar on vent pipe immediately

above flashing. Apply Dow Corning Silastic 732

RTV Sealant between vent pipe and storm collar

to provide weathertight seal.

f. Attach vent terminal.

Vent Terminal and Air Intake Terminal

14. Join vent terminal to 45° elbow (supplied by

installer). Join 45° elbow/terminal assembly to vent

pipe. Refer to Section C for proper procedures for

joining vent pipe and fittings. See Figure 3.

15. Install supplied air intake terminal. See Figure 16.

1. Do not exceed maximum vent length. Refer to

Table 4.

Horizontal

2. Maintain minimum ¼ inch per foot slope in

horizontal runs. Position weld seams in vent pipes,

in all horizontal runs, at the top to avoid condensate

from lying on the seams.

3 Recommended horizontal installation consists of

vent being sloped down away from boiler. See

Figure 12.

4. Alternate horizontal installation consists of vent

being sloped down toward the boiler. A horizontal

vent tee is required. See Figure 13.

5. Use appropriately designed thimbles when passing

through combustible walls (thimble use optional

for noncombustible walls). Insert thimble through

wall from outside. Secure outside flange to wall

with nails or screws, and seal with sealant material.

Install inside flange to inside wall, secure with nails

or screws, and seal with sealant material.

6. For noncombustible wall application when thimble

is not used, size opening such that female (bell) end

with locking band attached cannot pass through.

7. Join vent terminal to vent pipe. Locate vent

terminal between seventeen (17) inches and twenty-

nine (29) inches from wall when joined to inside

vent piping. See Figure 14.

8. Insert vent pipe through thimble/opening from

outside and join to vent system. Apply sealant

between vent pipe and opening/thimble to provide

weathertight seal.

Vertical

10. Installation of a vertical vent drain tee is required

on all vertical vent applications. See Figure 6.

Attach vertical vent drain tee directly to elbow or

horizontal pipe from an elbow immediately after

vent connector.

H.