beautypg.com

Notice – Burnham SCG 1100-H4 User Manual

Page 23

background image

COMBINATION hORIZONTAl VENT SySTEM COMPONENTS

F.

Combination Horizontal Venting System –SCG-3 Through SCG-6 ONLY – See Figures 10 and 11.

1. Do not exceed maximum vent/air intake lengths.

Refer to Table 4.

2.

Install Combination Vent/Air Terminal.

See Figure 11.

a. After determining the location with reference to Section B - General Venting Guidelines, cut a 6-1/8 inch square

opening in the wall for the air box sub-assembly which is 6 inch square.

b. Remove and save shipping screw from end panel with collar and vent pipe assembly. This will be reinstalled in a later

step.

NOTICE

This vent system requires components not

supplied with the boiler.

Vent Carton Part Number 61106012 (Includes Items Below)

Description

Component Part Number

A Air Box Sub-Assembly (6” square x 2’ long)

61106011

B Exterior Wall Cover (10” square)

71106016

C 4” x 3” Vent Pipe Reducer

8116239

D Plate-Seal Exterior Cover (2)

71106017

E #8 x ½” Stainless Steel Sheet Metal Screw (19)

80860047

F #10 - 32 x ¼” Stainless Steel Machine Screw (8)

80860842

G #10 - 32 x ½” Aluminum Spacer (4)

80861617