a. Wipe the male end of each joint using an alcohol

pad to remove any dirt and grease.

b. Align weld seams in pipes and use a slight

twisting motion to FULLY insert male end into

female end of joint. Ensure bead in male end

of pipe is below locking band and rest against

the end of the female pipe. Verify the factory-

installed gasket is not dislodged or cut.

c. Tighten locking band by HAND with a 5/16”

nut driver until snug plus ¼ turn. DO NOT

SECURE JOINTS WITH SHEET METAL

SCREWS OR POP RIVETS. DO NOT

PUNCTURE THE VENT SYSTEM!

d. Once the installation is complete, operate

appliance and inspect all joints to ensure that flue

gases and/or liquid condensate will not escape.

D.

Separate Horizontal Venting System.

See Figures

4A, 4B, 5A and 5B. See Figure 43 on Page 72 for

Blower Vent Connector Assembly.

Vent Piping

1. This boiler is supplied with components as standard

equipment for installation of the separate horizontal

venting system.

2. Do not exceed maximum vent/air intake lengths.

Refer to Table 4.

3. Recommended horizontal installation consists

of vent being sloped down ¼ inch per foot away

from boiler. See Figure 4A. See Figure 48 for an

alternate horizontal installation.

4. Use appropriate designed thimbles when passing

through combustible walls (thimble use optional for

noncombustible walls). Insert thimble through wall

from outside. Secure outside flange to wall with

nails or screws, and seal ID, OD and vent holes with

sealant material. Install inside flange to inside wall,

secure with nails or screws, and seal with sealant

material.

5. For noncombustible wall application when thimble

is not used, size opening such that bell with locking

band attached cannot pass through.

6. Join vent terminal to vent pipe. See Figures 5A and

5B.

7. Insert vent pipe through thimble/opening from

outside and join to vent system. Apply sealant

between vent pipe and opening/thimble to provide

weathertight seal.

Air Intake piping

- See Figures 4A, 4B, 5A and 5B.

8. Locate air intake termination on the same wall as

the vent termination if possible, to prevent nuisance

boiler shutdowns. However, boiler may be installed

with vertical venting and sidewall combustion air

inlet or visa versa, if installation conditions do not

allow alternate arrangement.

9. Do not exceed air intake length. See Table 4.

10. Use single wall metal or PVC pipe.

a. Air intake pipe diameter is based on boiler size.

SCG-3 & SCG-4 uses 3 inch diameter piping.
SCG-5 & SCG-6 uses 4 inch diameter piping.
SCG-7 thru SCG-9 uses 5 inch diameter piping.

11. Air intake termination must be located:

Horizontal - At least twelve (12) inches above

grade plus the expected snow accumulation.

12. Start at collar on boiler jacket and work towards the

air intake terminal.

13. Maintain minimum of ¼ inch per foot slope on

horizontal runs. Slope towards air inlet terminal

when possible. If not, slope towards boiler.

14. The air intake pipe must be adequately supported

with straps or supports no less than five (5) feet

apart on horizontal runs. The complete air intake

piping system must be rigid and able to withstand

minor impacts without collapse.

15.

Inlet air pipe penetration

:

Horizontal - Size wall penetration to allow easy

insertion of air inlet piping. Seal around pipe with

sealant to form weathertight exterior joint.

16. Seal all joints airtight, using silicone caulk or self-

adhesive aluminum tape.

17.

Install Air Intake Terminal

:

Horizontal - Remove four (4) screws from cover

plate and remove cover plate from terminal. Insert

intake piping into intake terminal collar. Secure

terminal to intake piping and seal joint with silicone

caulk or self-adhesive aluminum tape. Apply

continuous bead of silicone caulk around the back

of the intake terminal, approximately ¼ inch from

its edge. Push inlet terminal inward until terminal’s

back flange is against the wall surface. Secure the

terminal with noncorrosive fasteners (stainless steel,

brass or aluminum) to the wall. Reinstall the cover

plate with four (4) screws. Apply a bead of silicone

caulk to perimeter of intake terminal’s back flange

to provide a weathertight seal.