Installation, Before you begin, Site requirements – ElmoMC AC Input Digital Servo Drives-Bassoon Cable Kit User Manual
Page 15: Hardware requirements, Ac input requirements, Site requirements 1.10.2. hardware requirements

Cornet Installation Guide
MAN-CORIG (Ver. 1.502)
15
3.
Installation
The Cornet must be installed in a suitable environment and properly connected to its voltage
supplies and the motor.
1.10. Before You Begin
1.10.1. Site Requirements
You can guarantee the safe operation of the Cornet by ensuring that it is installed in an
appropriate environment.
Feature
Value
Ambient operating temperature
0 °C to 40 °C (32 °F to 104 °F)
Maximum Operating Altitude
2,000 m (6562 feet)
Maximum relative humidity
90% non-condensing
Operating area atmosphere
No flammable gases or vapors permitted in area
Models for extended environmental conditions are available.
Caution:
The Cornet dissipates its heat by forced ventilation (fan). The maximum operating
ambient temperature of 0 °C to 40 °C (32 °F to 104 °F) must not be exceeded.
1.10.2. Hardware Requirements
The components that you will need to install your Cornet are in this section.
1.10.2.1.
AC Input Requirements
Circuit Breakers &
Contacts
Three-Phase Supply
Voltage
Single-Phase Supply
Voltage
Circuit breaker current rating
150% to 200% of drive current 200% to 300% of drive current
Circuit breaker voltage rating
480 VAC
480 VAC
Contactor
Up to 150% of drive current
Up to 200% of drive current