SENSOR INSTALLATION

7.1

Class I, Division 2, Groups A, B, C, and D Rated
Equipment

Equipment so marked is suitable for use in Class I, Division 2,
Groups A, B, C, and D or non-hazardous locations only.

WARNING – EXPLOSION HAZARD – Do not disconnect
equipment unless power has been removed or the area is known
to be non-hazardous.

WARNING – EXPLOSION HAZARD –Substitution of components
may impair suitability for Class I, Division 2.

WARNING – EXPLOSION HAZARD –Do not replace fuses unless
power has been switched off or the area is known to be non-
hazardous.

WARNING – EXPLOSION HAZARD –Ensure a sensor band
shorting plug is installed on the sensor band cable connector
during installation and removal from process pipe.

7.2

Tools Required For Installation

The following tools are required for system installation. Additional
tools may be required based on particular installation needs.

Required Tools

Recommended Tools

Cable cutter

Wire number markers

Wrenches, 1/2 “x 9/16”, combination,
open-end, 2 ea

Portable electric screw driver with 7/64”
hex driver bit

Wire strippers for 20 gauge wire

Open end or combination wrench set

Allen wrench or hex driver, 7/64-inch for
No. 6 socket head cap screw, or 5/32-
inch for No. 10 socket head cap

Spring clamps to hold cover halves in
place temporarily

Spacer tool, sensor fastener (provided
with sensor band)

Cable jacketing removal tool

Screw drivers, Blade, 3/16” and 1/4”,
Phillips medium blade

Hacksaw and or armor cutter (armored
cable cutting)

14” Adjustable wrench (armored cable)

Socket wrench set

Sandpaper, cleaning rags, etc as
required for pipe cleaning

Volt-ohm meter

BAND-IT

®

Tool Model C001 (or

equivalent) for use with stainless steel
covers. Refer to www.band-it-idex.com
for distributor information.

Electricians tape

Table 2

Installation Tools For SONARtrac