Maintenance – Parts Replacement

990-2282A-001

Smart-UPS® VT 10-40 kVA 400V, 208V, 200V – Operation

31

Follow the below procedures if you need to change or add a battery module, e.g. if you receive a display

message reporting a bad battery, or if you need to add batteries for increased runtime.

Installation.

If additional batteries are needed for extra runtime, or if you install battery replacement

modules, be aware of the following:

When removing Battery Modules, start from

the highest level and work down.

Holding the battery handle, gently push the

battery upwards and pull it halfway out of

the enclosure. A lock mechanism prevents it

from being pulled all the way out.

To release the battery from the lock

mechanism, gently push the battery upwards

again and pull it out, while another person

supports the battery.

Caution

Batteries must be replaced by trained personnel only (see the section General safety
prior to Battery Module
replacement).

Caution

Do not install Battery Modules in the UPS until you are ready to power up the system.
Disregarding this caution can result in a deep discharge of the batteries and cause
permanent damage. The time between battery installation and powering up the UPS
should not exceed 72 hours or 3 days.