beautypg.com

APC Smart-UPS VT User Manual

Page 23

background image

Operation – Operation Procedures

990-2282A-001

Smart-UPS® VT 10-40 kVA 400V, 208V, 200V – Operation

17

Total power off – single system with MBP.

Total power off – parallel system.

For details on how to remove Battery Locks (if available) see the section How to remove
and install battery locks (if available)
.

Check that the load is OFF.

From the UPS: Turn load

OFF

the UPS from

the display via Control–Turn Load off–Yes,

turn Load off.

From the external MBP: Turn the output

switch

(Q002)

to position “0”

(OFF)

.

From the external MBP: Turn the input switch

(Q001)

to position “0”

(OFF)

.

From the XR Enclosure(s) (if available): Set

the DC disconnect switch (if available) on the

XR Enclosure(s) to the

OFF

position.

From the UPS: Disconnect the batteries in the

UPS by pulling them out to the red disconnect

line.

From the XR Enclosure(s) (if available):

Disconnect the batteries by pulling them out to

the red disconnect line.

Check that the load is OFF.

From the UPS: Turn load

OFF

each of the UPS

units from the display via ControlTurn

Load off–Yes, turn Load off.

From the external MBP: Turn the output

isolation breaker

(Q004)

to position “0”

(OFF).

From the external MBP: Turn all output

switches

(Q002)

to position “0”

(OFF)

.

From the external MBP: Turn all input

switches

(Q001)

to position “0”

(OFF)

.

From the XR Enclosure(s) (if available): Set

the DC disconnect switch (if available) to the

OFF

position.

From the UPS: Disconnect the batteries in the

UPS units by pulling them out to the red

disconnect line.

From the XR Enclosure(s) (if available):

Disconnect the batteries on the UPS units by

pulling them out to the red disconnect line.