APC Smart-UPS VT User Manual

Page 25

background image

Operation – Operation Procedures

990-2282A-001

Smart-UPS® VT 10-40 kVA 400V, 208V, 200V – Operation

19

How to perform a restart

Restart – single system wihout external MBP.

Set the utility/mains breaker to the

ON

position.

If your installation includes an XR Battery Enclosure (SUVTBXR2B6S/SUVTBXR6B6S) with a

DC disconnect switch, set the DC disconnect switch to the

ON

position.

After system boot-up, the display will automatically ask you to confirm/select voltage and frequency as
shown in the following.

Voltage confirmation.

At restart, the display will prompt you through the following screens:

Warning

Only trained personnel familiar with the construction and the equipment may

restart the UPS.

Note

Wait approximately 30 seconds for the system to boot up and carry out a self test.

When the Confirm Voltage prompt appears on
the screen, go to the desired voltage using the

UP/

DOWN

keys and press

ENTER

.

When the prompt Apply load appears, go to Yes
using the

UP/DOWN

keys and press

ENTER

if you

want the UPS to provide a load output now. (If
you do not want UPS load output at this point, go
to No).

The green (

LOAD ON

) LED is now lit. Press

ESC

two times and the display will show the above
Overview Screen.

Note

The UPS is now ready to support the load.

Confirm Voltage
Use 400V
Yes, use 400V
No, select another

Use

Press

Apply load?
Yes
No

Use

Press

Chrg xxx% ||||||||||
Load xxx% ||||||||||
xxx Vin xxxVout xxHz
Run-time: xxhr xxmin