APC Smart-UPS VT User Manual
Page 27

Operation – Operation Procedures
990-2282A-001
Smart-UPS® VT 10-40 kVA 400V, 208V, 200V – Operation
21
Restart – parallel system.
Warning
Only trained personnel familiar with the construction and the equipment may
restart the UPS system.
From the XR Enclosure(s) (if available):
Connect the batteries on the UPS units by
pushing them in.
From the UPS: Connect the batteries by
pushing them in.
From the XR Enclosure(s) (if available): Set
the DC disconnect switch (if available) to the
ON
position.
From the external MBP: Turn all input
switches
(Q001)
to position “1”
(ON)
.
From the external MBP: Turn all output
switches
(Q002)
to position “1”
(ON)
.
From the external MBP: Turn the output
isolation breaker
(Q004)
to position “1”
(ON)
.
From the UPS: Turn load ON each of the UPS
units from the display via Control
–
Turn
Load on
–
Yes, turn Load on.
Check that the load is
ON
.
Note
The UPS system is now ready to support the load.
Note
Auto-detection on frequency – if a problem occurs call APC Customer Support (see the
back cover of this manual).